How to optimise the system:
1. Log in and load project.
2. Check the task processing times.
3. Optimising the cycle times:
If required technologically, the cycle times of the remaining tasks with lower
priorities can be decreased.
Condition: No task with a low priority may assign more than 60 percent of the
corresponding cycle time in its task utilisation.