Commissioning
Before switching on
8
123
EDS700ACBA EN 4.0
8 Commissioning
Note!
ƒ Please observe the general safety instructions ( 13).
ƒ Please observe the notes regarding residual hazards ( 18).
8.1 Before switching on
Prevent injury to persons and damage to property by checking the following before
switching on the mains voltage.
Check
ƒ the wiring for completeness.
ƒ for the absence of short circuits and/or earth faults.
ƒ for the correct covering of the DC−bus wiring.
ƒ the "EMERGENCY OFF" function of the entire system.
ƒ the motor circuit configuration (star/delta). It must be adapted to the output
voltage of the controller.
ƒ the in−phase connection of the motor (direction of rotation).
ƒ whether the drive mechanically can be disconnected from the machine for
commissioning.
Danger!
High hazard potential during commissioning
Incorrect settings can cause unexpected and dangerous movements of the
motor and the equipment.
Possible consequences:
ƒ Damage to material assets
ƒ Injury to persons
Protective measures:
ƒ Clear hazard area
ƒ Observe safety instructions and safety distances
8.2 Quick commissioning
Quick commissioning is described in
ƒ the "Controller−based automation, EtherCAT" communication manual,
– the chapter "Commissioning of i700 servo inverter".